Question 1

Which statement describes a mitigated ART PI Risk?


Correct : C

A mitigated ART PI Risk is one that has an agreed-upon plan for alleviation, which may involve changing the scope, schedule, or resources of the PI. This reduces the impact or likelihood of the risk, but does not eliminate it completely


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

In a 12-week PI, how often does the Innovation and Planning (IP) Iteration occur?


Correct : A

The Innovation and Planning (IP) Iteration is a unique, dedicated iteration that occurs every Program Increment (PI). A PI is a timebox of 8 to 12 weeks, during which an Agile Release Train (ART) delivers incremental value in the form of working, tested software and systems. Therefore, in a 12-week PI, the IP Iteration occurs every quarter


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

What is a pattern for splitting Features into Stories?


Correct : B

A pattern for splitting Features into Stories is to use variations in data, which means identifying different types of data that the feature can handle and creating a story for each type. For example, a feature that allows users to upload files can be split into stories for different file formats, sizes, or sources. This way, the stories are independent, testable, and valuable12


* Story - Scaled Agile Framework

* User stories splitting by data variations and interfaces

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

What is one strategy for managing complex critical path challenges?


Correct : A

One strategy for managing complex critical path challenges is to adjust work between teams or split Features and Stories. Complex critical path challenges are situations where the delivery of value depends on the completion of multiple interdependent tasks by different teams1. These challenges can cause delays, bottlenecks, and inefficiencies in the value stream. To overcome these challenges, one option is to adjust work between teams or split Features and Stories, so that the dependencies are minimized or eliminated2. This can help improve the flow of work, reduce the risk of integration issues, and increase the flexibility and responsiveness of the teams3.


* Accelerating Flow with SAFe - Scaled Agile Framework

* Managing Dependencies - Scaled Agile Framework

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

What is one strategy for managing complex critical path challenges?


Correct : C

One effective strategy for managing complex critical path challenges in SAFe is to adjust the allocation of work between teams or to split features and stories. This approach allows for more flexibility in managing dependencies and workload distribution, ensuring that teams can adapt to changes and maintain progress on the critical path.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500