Curious about Actual SAP Certified Associate (C_TS422_2023) Exam Questions?
Here are sample SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing (C_TS422_2023) Exam questions from real exam. You can get more SAP Certified Associate (C_TS422_2023) Exam premium practice questions at TestInsights.
What does a line hierarchy in repetitive manufacturing represent?
Correct : A
The other options are not correct for the following reasons:
A production line with prioritized work centers(B): This is not correct. A line hierarchy does not define the priority of the work centers, but the order and the dependency of the work centers. The priority of the work centers can be determined by other factors, such as the capacity availability, the production rate, or the scheduling parameters.
Start a Discussions
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.
Correct : A, B, E
Increase the capacity supply in a time-phased interval: You can use the capacity planning table or the capacity planning board to increase the available capacity of a resource by changing the shift sequence, the shift duration, or the number of individual capacities. You can also use the capacity leveling function to distribute the capacity requirements over a longer time horizon. This way, you can avoid capacity overloads and create a balanced capacity load.
Determine a time period with available capacity on the planning board: You can use the planning board to visualize the capacity load and the capacity availability of a resource in a graphical Gantt chart. You can use the filter and zoom functions to focus on a specific time period and resource. You can also use the capacity evaluation function to display the capacity situation in a tabular or graphical form. This way, you can identify the time periods with available capacity and plan the operations accordingly.
Start a Discussions
Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing?
Note: There are 2 Correct answers to this question?
Correct : B, C
Run PP/DS heuristic for repetitive manufacturing: PP/DS (Production Planning and Detailed Scheduling) is a component of SAP S/4HANA that provides advanced planning and scheduling functions for complex production scenarios. You can run the PP/DS heuristic for repetitive manufacturing to automatically assign planned orders to production lines based on the available capacity, material, and sequence constraints. The PP/DS heuristic also optimizes the line utilization and minimizes the setup times and costs.
Assign planned orders manually in the planning table: The planning table is a graphical tool that allows you to view and manipulate the production plan for repetitive manufacturing. You can assign planned orders manually to production lines by dragging and dropping them in the planning table. You can also adjust the start and finish dates, quantities, and sequences of the planned orders. The planning table shows the capacity situation and the material availability for each production line.
You cannot plan both quantities and capacities during line loading in repetitive manufacturing by using the following options:
Run MRP with quota arrangement: MRP (Material Requirements Planning) is a process that calculates the quantity and timing of material requirements based on the demand and supply situation. You can run MRP with quota arrangement to distribute the total requirements for a material among multiple sources of supply, such as vendors, plants, or production lines. However, MRP does not consider the capacity constraints or the sequence dependencies of the production lines, and therefore cannot plan the capacities during line loading.
Assign planned orders manually in the planning table: This option is identical to option C and therefore cannot be a correct answer.
Start a Discussions
which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?
Correct : A, C
1: SAP Help Portal: Mass Processing
2: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 7: Process Orders
3: SAP Help Portal: Trigger Points
: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 6: Production Orders
Start a Discussions
How would you define pegging in the context of Advanced Planning?
Correct : B
Start a Discussions
Total 80 questions