Curious about Actual SAP Certified Associate (C_TS422_2023) Exam Questions?

Here are sample SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing (C_TS422_2023) Exam questions from real exam. You can get more SAP Certified Associate (C_TS422_2023) Exam premium practice questions at TestInsights.

Page: 1 /
Total 80 questions
Question 1

What does a line hierarchy in repetitive manufacturing represent?


Correct : A

A line hierarchy in repetitive manufacturing represents the structure of a production line that consists of multiple work centers. A line hierarchy is a master data object that defines the sequence and the relationship of the work centers that are involved in producing a material. A line hierarchy can be split into different levels, such as line segments, processing stations, or takt areas, to reflect the complexity and the variability of the production line.A line hierarchy can be used for planning and scheduling operations, controlling material flow, and monitoring production performance12.

The other options are not correct for the following reasons:

A production line with prioritized work centers(B): This is not correct. A line hierarchy does not define the priority of the work centers, but the order and the dependency of the work centers. The priority of the work centers can be determined by other factors, such as the capacity availability, the production rate, or the scheduling parameters.

A production line with a parallel sequence in the routing: This is not correct. A line hierarchy does not represent the parallel sequence in the routing, but the linear sequence of the work centers. A parallel sequence in the routing means that two or more operations can be performed simultaneously on different work centers for the same material.A parallel sequence in the routing can be modeled by using alternative sequences or parallel sequences in the line hierarchy3.

A production line with an alternative sequence in the routing(D): This is not correct. A line hierarchy does not represent the alternative sequence in the routing, but the main sequence of the work centers. An alternative sequence in the routing means that there are different options for performing an operation on different work centers for the same material.An alternative sequence in the routing can be modeled by using alternative sequences or parallel sequences in the line hierarchy3.


https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/9231f9504a62eb5ee10000000a44538d.html

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.


Correct : A, B, E

Increase the capacity supply in a time-phased interval: You can use the capacity planning table or the capacity planning board to increase the available capacity of a resource by changing the shift sequence, the shift duration, or the number of individual capacities. You can also use the capacity leveling function to distribute the capacity requirements over a longer time horizon. This way, you can avoid capacity overloads and create a balanced capacity load.

Determine a time period with available capacity on the planning board: You can use the planning board to visualize the capacity load and the capacity availability of a resource in a graphical Gantt chart. You can use the filter and zoom functions to focus on a specific time period and resource. You can also use the capacity evaluation function to display the capacity situation in a tabular or graphical form. This way, you can identify the time periods with available capacity and plan the operations accordingly.

Form optimum sequence to reduce setup times: You can use the setup matrix or the setup group key to define the setup times and the setup categories for a resource. You can also use the setup optimization function to determine the optimum sequence of operations that minimizes the total setup time. This way, you can reduce the capacity consumption and increase the throughput of the resource.Reference:Identifying the Basic Principles and Tools of Capacity Planning;SAP Help Portal; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 82.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing?

Note: There are 2 Correct answers to this question?


Correct : B, C

Run PP/DS heuristic for repetitive manufacturing: PP/DS (Production Planning and Detailed Scheduling) is a component of SAP S/4HANA that provides advanced planning and scheduling functions for complex production scenarios. You can run the PP/DS heuristic for repetitive manufacturing to automatically assign planned orders to production lines based on the available capacity, material, and sequence constraints. The PP/DS heuristic also optimizes the line utilization and minimizes the setup times and costs.

Assign planned orders manually in the planning table: The planning table is a graphical tool that allows you to view and manipulate the production plan for repetitive manufacturing. You can assign planned orders manually to production lines by dragging and dropping them in the planning table. You can also adjust the start and finish dates, quantities, and sequences of the planned orders. The planning table shows the capacity situation and the material availability for each production line.

You cannot plan both quantities and capacities during line loading in repetitive manufacturing by using the following options:

Run MRP with quota arrangement: MRP (Material Requirements Planning) is a process that calculates the quantity and timing of material requirements based on the demand and supply situation. You can run MRP with quota arrangement to distribute the total requirements for a material among multiple sources of supply, such as vendors, plants, or production lines. However, MRP does not consider the capacity constraints or the sequence dependencies of the production lines, and therefore cannot plan the capacities during line loading.

Assign planned orders manually in the planning table: This option is identical to option C and therefore cannot be a correct answer.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

which of the following automation options can you use for production orders? Note: There are 2 Correct answers to this question?


Correct : A, C

You can use mass processing to set production orders to technically complete. Mass processing allows you to perform the same action for multiple production orders at once, such as changing the status, printing, or confirming. You can use the Set to Technically Complete action to close the production orders that are finished and do not require any further processing.This action updates the order status to TECO and prevents any further changes to the order12.

You can use trigger points to automatically create rework orders via confirmation. Trigger points are predefined events that occur during the execution of a production order, such as reaching a certain operation or quantity. You can assign actions to trigger points, such as creating a notification, a rework order, or a quality inspection. For example, you can use a trigger point to automatically create a rework order for defective goods when you confirm an operation.The rework order is linked to the original order and inherits the relevant data from it3.


1: SAP Help Portal: Mass Processing

2: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 7: Process Orders

3: SAP Help Portal: Trigger Points

: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 6: Production Orders

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

How would you define pegging in the context of Advanced Planning?


Correct : B

Pegging is a term used in Advanced Planning to describe the relationship between the receipt and the issue elements of a product within a location. Receipt elements are planning elements that increase the stock of a product, such as production orders, purchase orders, or stock transfers. Issue elements are planning elements that reduce the stock of a product, such as sales orders, planned independent requirements, or reservations. Pegging links the receipt and issue elements according to the bill-of-material structure of all related products and represents the material flow through all levels of production. Pegging enables the system to identify and display quantity and date/time problems, such as shortages or delays, and to forward scheduling changes to other dependent elements.Pegging also forms the basis for the availability check and the capacity check in Advanced Planning12.


1: SAP Help Portal: Pegging

2: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 4: Advanced Planning

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Page:    1 / 16   
Total 80 questions