Question 1

Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.

What benefit do they have when using delivery from project (CNSO).


Correct : D

Delivery from project (CNSO) is a function that allows you to deliver material components that are assigned to network activities in a project. You can use this function to generate goods issues for project stock without creating delivery documents. You can also use this function to create delivery documents for sales order stock or plant stock that are assigned to network activities. Delivery from project helps you to reduce the effort and time required for delivering materials in a project. Reference: https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e10000000a174cb4/frameset.htm


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?

Note : there are 3 correct answer for this question.


Correct : B, C, E

A template is a predefined structure that can be used to create a new project with network in the Project Builder (CJ20N). You can use different types of templates depending on your requirements and preferences. Some of these templates are:

Standard network: This is a template that contains predefined activities, relationships, milestones, and components for a network. You can use a standard network to create a new network with similar structure and content.

Standard Project definition: This is a template that contains predefined WBS elements, networks, activities, relationships, milestones, and components for a project. You can use a standard project definition to create a new project with similar structure and content.

Project definition: This is an existing project that can be used as a template for creating a new project with network. You can use a project definition to copy the entire structure and content of an existing project or only selected parts of it. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

The various work packages in the project are described as individual______________. Choose the correct answer.


Correct : D

The various work packages in the project are described as individual activities. Activities are the smallest units of a project that can be planned, executed, and controlled. Activities can be assigned to one or more WBS elements in a project. Activities can also be linked to each other by relationships to define the sequence and dependencies of the work packages. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

Materials

Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set

of dates that can be scheduled.

Which set of dates can be used for scheduled for network?

Note : there are 2 correct answer for this question.


Correct : A, E

In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:

Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.

Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

Which statement regarding the creation of a new work breakdown structure (WBS element) are true?

Note : there are 3 correct answer for this question.


Correct : A, C, D

You can create several WBS elements per level.'' According to SAP Help Portal2, ''You can assign a WBS element of the new project to a different project definition.'' According to SAP Help Portal3, ''WBS elements can be planning elements, account assignment elements, and billing elements at the same time.'' Reference:123


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500