Question 1

What function commits funds assigned to the budget of a WBS element?


Correct : A

Availability Control (A) is the function that commits funds assigned to the budget of a WBS (Work Breakdown Structure) element. It monitors budget consumption and can issue warnings or prevent further postings when budget limits are exceeded, ensuring that project spending stays within approved budgets. Reference = SAP Project System (PS) documentation and financial controls guides.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

Which controlling objects can be settled by a settlement rule in SAP S/4HANA? Note: There are 3 correct answers to this question


Correct : A, B, C

Controlling objects that can be settled by a settlement rule in SAP S/4HANA include Production Orders (A), Maintenance Orders (B), and WBS Elements (C). Settlement rules define how costs collected on these objects are allocated to other cost receivers, such as cost centers, projects, or fixed assets, for accurate cost tracking and analysis. Reference = SAP Controlling (CO) and Project System (PS) documentation.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

When is backorder processing considered?


Correct : B

Backorder Processing is considered when the Order Quantity is Not Fully Confirmed (B). This process involves reallocating available stock to prioritize important orders, ensuring that critical orders are fulfilled as quickly as possible, even in situations where inventory levels are insufficient to meet all demand immediately. Reference = SAP Sales and Distribution (SD) and Advanced Planning and Optimization (APO) documentation.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

Which backorder processing (BOP) strategy has first processing priority and is used to release confirmed stock to prioritize other orders to plan future stock needs?


Correct : C

The 'Win' backorder processing (BOP) strategy has first processing priority and is used to release confirmed stock to prioritize other orders and plan for future stock needs. This strategy helps in reallocating available inventory to more critical orders, ensuring that the most important demands are met first. Reference = SAP Advanced Planning and Optimization (APO) and Sales and Distribution (SD) documentation.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

What planning tool prioritizes sales order forecasting and strategically plans inventory buffers?


Correct : B

Demand-Driven MRP (DDMRP): DDMRP is an innovative planning method that combines aspects of traditional MRP, Lean, and Six Sigma to strategically position inventory buffers to meet customer demand while minimizing lead times and variability.

Key Features of DDMRP:

Sales Order Forecasting: DDMRP uses demand-driven planning, focusing on actual customer orders and demand signals to prioritize production and inventory management.

Inventory Buffers: Strategically placed inventory buffers absorb variability in supply and demand, ensuring optimal inventory levels to meet customer needs without excess.

Implementation in SAP: SAP S/4HANA incorporates DDMRP capabilities, allowing businesses to implement this approach for more responsive and efficient supply chain management.


SAP S/4HANA Demand-Driven MRP Guide

Demand Driven Institute Resources on DDMRP

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500