Curious about Actual PMI PMP (PMI-RMP) Exam Questions?

Here are sample PMI Risk Management Professional (PMI-RMP) Exam questions from real exam. You can get more PMI PMP (PMI-RMP) Exam premium practice questions at TestInsights.

Page: 1 /
Total 203 questions
Question 1

Rob is the project manager of the IDLK Project for his company. This project has a budget of $5,600,000 and is expected to last 18 months. Rob has learned that a new law may affect how the project is allowed to proceed - even though the organization has already invested over $750,000 in the project. What risk response is the most appropriate for this instance?


Correct : A


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to the perform quantitative risk analysis process?


Correct : D


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don were to perform a risk audit, who would carry the risk in this scenario?


Correct : C


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

You are the project manager of the BlueStar project in your company. Your company is structured as a functional organization and you report to the functional manager that you are ready to move onto the qualitative risk analysis process. What will you need as inputs for the qualitative risk analysis of the project in this scenario?


Correct : B


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

Todd is the project manager of the EST project for his company. His organization has established certain rules in the enterprise environmental factors which affect the approach that Todd takes in managing his project. One of the rules requires Todd to consider the risk attitude of the stakeholders participating in risk analysis. Why must risk attitude be considered as a part of risk analysis?


Correct : A


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Page:    1 / 41   
Total 203 questions