Question 1

To help ensure compliance with the US Code of Federal Regulations (21 CFR Part 11), your client wants to enable audit trail for manufacturing work definitions and standard operations.

Which is NOT included in the audit trail for standard operations such as creation, update, and deletion?


Correct : C

When enabling audit trail functionality to ensure compliance with the US Code of Federal Regulations (21 CFR Part 11), certain actions related to work definitions and standard operations are audited for changes such as creation, update, and deletion. However, not all aspects are tracked in the audit trail.

Item structure component attributes referenced from Product Information Management (PIM) are not included in the audit trail. PIM attributes are managed separately from manufacturing-specific data, and changes to these components are not captured in the standard operations audit trail.

Audited components typically include:

Work definition header and version attributes

Descriptive flexfields (DFFs) at any level

Attachments at any level

Operation resources, including alternate resources


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

Your customer is a light assembly manufacturing company that doesn't require shop floor control. A Manufacturing Engineer wants to generate a work definition automatically for some items, and wants to eliminate the explicit maintenance of work definitions.

Which three steps must they perform and verify in the Work Definition area?


Correct : A, B, E

In light assembly manufacturing environments where shop floor control is not required, a Manufacturing Engineer can automate the creation of work definitions to streamline production processes. The following steps must be performed and verified:

Select a resource to be used in automatic work definition by enabling the Default attribute. This ensures that the system can automatically assign resources to the work definition without manual intervention.

Ensure the predefined work definition name ORA_MAIN is active, as this serves as the template for automatically generating work definitions in the system.

Select a standard operation for use in automatic work definition, also by enabling the Default attribute. This ensures that the system knows which operations to include in the work definitions.

Incorrect steps:

C: Secondary item structure is not relevant for automatic work definitions.

D: There can be multiple default operations, so it's not necessary to limit it to one.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

Which three can you set as Overcompletion Tolerance Type and its value for a subcomponent yield, so that the job order can report the excess production completion?


Correct : B, D, E

In Oracle Manufacturing Cloud, overcompletion tolerance allows for the reporting of excess production completion beyond the planned amount. The overcompletion tolerance type and value determine how much extra production can be reported:

Percentage, value = 100 allows the system to accept overcompletion of up to 100% more than the planned quantity.

Amount, value > 0 specifies a fixed amount by which overproduction can be tolerated.

Percentage, value > 0 allows overproduction by a percentage greater than 0 but less than 100.

Incorrect settings:

A: Setting the percentage to 0 means no overcompletion is allowed.

C: An amount of 0 also means no excess production can be reported.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

In the work execution area, which three infolets are provided to users for instant access?


Correct : A, C, E

In the Work Execution area of Oracle Manufacturing Cloud, several infolets provide users with quick access to critical data. The following infolets are available for immediate access:

Work Order Performance: Provides an overview of the performance of work orders against the planned schedule, showing progress and efficiency.

Operation Exception: Highlights any exceptions or issues encountered during operations, enabling quick identification of problems.

Work Order Exception: Displays any issues or exceptions related to work orders, such as delays or material shortages.

Incorrect options:

Scrap and Operation Efficiency are important metrics, but they are not available as standard infolets in the Work Execution area.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

Which three requirements are fulfilled by nonstandard work orders?


Correct : B, C, D

Nonstandard work orders in Oracle Manufacturing Cloud are used for specialized tasks that do not follow typical production processes. The following are the main requirements fulfilled by nonstandard work orders:

Repair: Nonstandard work orders can be used for maintenance and repair tasks to fix or refurbish defective or damaged items.

Rework: These work orders are also used for rework processes, where a product needs to be reprocessed to meet quality standards or specifications.

Prototype: Nonstandard work orders can handle prototype production, where items are produced in small quantities for testing and development before mass production.

Rescheduling (A) is typically handled by standard work orders in the production schedule rather than through nonstandard work orders.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Page:    1 / 10   
Total 50 questions