Curious about Actual Isaca COBIT 2019 Foundation Exam Questions?

Here are sample Isaca COBIT 2019 Foundation (COBIT-2019) Exam questions from real exam. You can get more Isaca COBIT Foundation (COBIT-2019) Exam premium practice questions at TestInsights.

Page: 1 /
Total 187 questions
Question 1

When defining a governance implementation roadmap. what is the NEXT step after planning the program?


Correct : D

After planning the implementation roadmap, the next step is to execute the plan. This involves taking the necessary steps to implement and actualize the governance plan. According to Isaca COBIT 2019, this includes tasks such as selecting a program manager, engaging stakeholders, selecting an implementation team, and initiating the program. Additionally, it is important to ensure that the program is properly monitored and that the progress is tracked.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

Which of the following is a KEY consideration when determining the initial scope of a governance system?


Correct : A

According to Isaca COBIT 2019, a key consideration when determining the initial scope of a governance system is the compliance requirements faced by the enterprise. This includes laws, regulations and other requirements which the enterprise must comply with. Additionally, it is important to consider the current IT-related issues of the enterprise and the role of IT within the enterprise, as well as the size of the enterprise.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

When tailoring COBIT 2019 to enterprise requirements, which of the following is the PRIMARY objective of preparing a risk profile?


Correct : D

According to Isaca COBIT 2019, the primary objective of preparing a risk profile is to identify areas of risk that exceed the risk appetite of the enterprise. This involves assessing the potential risks that the enterprise is exposed to, and determining if these risks exceed the level of risk that the enterprise is willing to accept. This helps the enterprise understand and prioritize the areas of risk that need to be addressed, and helps to ensure that appropriate measures are taken to mitigate these risks.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

What is the PRIMARY benefit of conducting a high-level risk analysis during governance design?


Correct : C

The primary benefit of conducting a high-level risk analysis during governance design is to prioritize governance and management objectives (Option C). This analysis helps to identify the areas of the enterprise that are most vulnerable to risks and prioritize the governance and management objectives based on the level of risk. The results of the risk analysis can then be used to determine the resources that are needed to mitigate the identified risks, and to develop a risk response strategy that aligns with the enterprise's risk appetite and objectives. The high-level risk analysis is an important step in the overall governance design process, as it helps ensure that the enterprise is taking proactive steps to manage risk and achieve its goals.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

At which stage of the EGIT implementation life cycle should the enterprise determine the impact of an improvement program on IT and the business and how to maintain the improvement momentum?


Correct : B

According to the official COBIT 2019 Study Manual from ISACA, when developing the EGIT implementation program plan, the enterprise should consider the impact of the improvement program on IT and the business. This includes analyzing the expected value from the implementation, such as cost savings or increased efficiency, as well as how to maintain the improvement momentum. This analysis should inform the strategy for implementing the EGIT program, as well as inform the selection of metrics and targets for measuring the effectiveness of the program.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Page:    1 / 38   
Total 187 questions