A Belt gathered the following defect data for a polyurethane production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data:Trimming37
Forming61
Packaging29
Sealing5
Correct : D
Start a Discussions
The length of wooden beams being sawed is measured by a line operator. Which is least likely to be influenced by the instrument?
Correct : C
Start a Discussions
Measurement System Analysis is a procedure used to quantify variation of the method or system used for taking measurements and used to assure usable data is collected.
Correct : A
Start a Discussions
One of the primary objectives of constructing an X-Y Diagram is to separate the vital few Y's from the trivial many Y's.
Correct : B
Start a Discussions
It is recommended that when beginning a 5S program it be started in a pilot work area for learning and demonstration purposes then it is expended throughout the plant.
Correct : A
Start a Discussions