Curious about Actual CompTIA Project+ (PK0-005) Exam Questions?

Here are sample CompTIA Project+ Certification (PK0-005) Exam questions from real exam. You can get more CompTIA Project+ (PK0-005) Exam premium practice questions at TestInsights.

Page: 1 /
Total 239 questions
Question 1

Which of the following PRINCE2 processes includes creating the project plan?


Correct : B

According to PRINCE2, a project management methodology, the process of initiating a project includes creating the project plan, which is a high-level plan that covers the whole project scope, schedule, budget, quality, and risks. The project plan is based on the project brief, the business case, and the product descriptions. The project plan is used to obtain the authorization from the project board to initiate and execute the project. The project plan is also refined and updated throughout the project life cycle as more information becomes available.

The other processes are not directly involved in creating the project plan. Starting up a project is a pre-project process that ensures the project is viable and worthwhile, and produces the project brief and the initiation stage plan. Managing product delivery is a process that coordinates the delivery of products from the team managers to the project manager, and ensures that the work conforms to the quality criteria and the project plan. Directing a project is a process that enables the project board to oversee and control the project, and make key decisions and approvals. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 5: Project Scope Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 5: Project Scope Management2; PRINCE2 Processes - 7 Processes Of PRINCE2 Explained3; Initiating a Project Process -- This process is the procedure which defines the product quality, Project Product, project timeline, costs, the commitment of resources, risk analysis, and assembles the Project Initiation Documentation (PID)4


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?


Correct : B

This is where an existing application that is highly utilized by clients is moving to a new release, as it involves deploying and operating it in a live environment.Reference= CompTIA Project+ Study Guide1, Chapter 4: Project Environments


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?


Correct : D

This is the process of gathering information directly from the client and other stakeholders to define what needs to be done in order to deliver the project outcomes.Reference= CompTIA Project+ Study Guide1, Chapter 9: Scope Management

According to the CompTIA Project+ Study Guide1, scope management is the process of defining, validating, and controlling the project scope throughout the project life cycle. Scope management involves identifying and documenting the project requirements, creating a work breakdown structure (WBS), and managing changes to the scope.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?


Correct : C

Quantitative risk analysis involves numerically analyzing the effect of identified risks on overall project objectives. It often includes assigning monetary values to risks to understand their impact in financial terms, helping in prioritizing risks based on their potential cost or impact on the project. This contrasts with qualitative risk analysis, which assesses risks based on their probability and impact but does not assign numerical values.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?


Correct : C

Language barriers can lead to misunderstandings within a global project team, causing misinterpretations of project requirements or features. In this case, the development team misinterpreted which features needed to be incorporated into the demo presentation due to communication issues, likely stemming from language differences. This highlights the importance of clear communication and understanding in a diverse project team.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Page:    1 / 48   
Total 239 questions