Juno is completing a Variance Analysis on the sales department's spend for the first quarter. He concludes that there is a Favourable Variance. What does this mean?
Correct : C
A favourable variance means that the actual performance was better than expected.
Start a Discussions
Danger Incorporated is estimating the costs for a new project called the Ninja Project using an algorithm based on the project's scope, duration, and complexity. What type of cost estimate is being used?
Correct : D
Using an algorithm based on key parameters is characteristic of a parametric cost estimate.
Start a Discussions
Cactus Construction is the Principal Contractor on a housing estate project under an NEC contract. Which of the following scenarios would be a mandatory variation?
Correct : C
Changes to building regulations are mandatory because they are legally binding and require compliance.
Start a Discussions
Sarah is a Project Manager running a project to create a new type of shoe that is sensitive due to intellectual property issues. She is undergoing Programme Level Control. What is the purpose of Programme Level Control?
Correct : B
Programme Level Control is used to ensure that adequate resources are allocated to complete the project on time.
Start a Discussions
Liability limitation often focuses on which of the following types of loss, which is said to be the most unpredictable and most significant in the case of a default on a contract?
Correct : D
Consequential loss is considered the most unpredictable and significant, hence it is often the focus of liability limitations.