Question 1

Michelle contacts Hannah and asks her if she would be interested in purchasing her car for 2000. Hannah immediately takes 2000 to Michelle and says she wants to buy the car. Michelle subsequently refuses to proceed. Has the contract between Michelle and Hannah been made?


Correct : A

To solve the question, you must distinguish the following notion:

- Offer: The case of Storer v Manchester City Council [1974] 1 WLR 1403 outlines that an offer is: An expression of willingness to contract on specified terms, with the intention that it is to be binding once accepted

- Acceptance: in order for a contract to be formed, the offer must be accepted. Acceptance represents the meeting of the minds of the parties to the contract -- both agree to exchange something for the other (payment, services, goods, etc.).

- Counter offer: is an offer made in response to a prior offer.

- Invitation to treat: An important distinction to make in contract law is that between an offer and an invitation to treat. An invitation to treat is usually an invitation for another party to make an offer. It may also be defined as an indication that a party is open to negotiation.

Here are some key distinctions of offers and invitation to treats.

Offer:

* Certain promise to be bound

* Clear and specified terms

* The conduct or words of the party show certainty

* There is no room for negotiation

Invitation to treat:

* There is room for negotiation

* There is an invitation for offers

* There is a request for information

* Lack of certainty

In the scenario above, initially Michelle just gives an invitation to treat because she is asking whether Hannah is interested to buy her car (request for information from Hannah). Hannah may reject or go into a negotiation with Michelle. Then, Hannah makes an offer by taking the money and shows her intention to be legally bound. At this point, when Hannah's offer is present, Michelle can accept or reject. When she rejects, the contract is not formed. The answer must be 'No, because Michelle has rejected Hannah's offer on buying the car'.


- Definition of Counter Offer

- Formation of the contract

- CIPS study guide page 28-35

LO 1, AC 1.2

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

Under which of the following scenarios an RFQ is most likely to be used?


Correct : A

The request for quotations is a procurement method that is used for small value procurements of readily available off-the-shelf goods, small value construction works, or small value services procurements. Request for quotations works best under a framework agreement

This procurement method is also known as invitation to quote and shopping, and it does not require the preparation of tender documents to the same extent as open tendering, request for proposals or two-stage tendering.

Among 4 options:

- 'Purchase of a small number of standardised products under a framework agreement': the products are standardised and there is a framework agreement in place, so RFQ is the best solution.

- 'Purchase of complex machinery': Complex machinery is often a large purchase. Furthermore, suppliers' quality may vary. So RFQ is not suitable, instead, depending on the situation, buyer may opt ITT or RFP to purchase this type of machinery.

- 'Design of a unique and complex software code': Unique and complex software is not off-the-shelf, thus RFQ is not suitable.

- 'When the buying organisation does not know the requirements in details and needs the input from suppliers': When the detailed requirements are unknown, the best solution is request for proposal or developing dialogue with suppliers.


- Request for Quotations

- CIPS study guide page 3-4

LO 1, AC 1.1

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

Which of the following are commonly used as model forms of contracts in construction in the UK?


Correct : B, D

- NEC: New Engineering Contract - a family of standard contracts primarily used in construction in the UK; includes works, consultants, services

- JCT: Joint Contracts Tribunal - a family of standard contracts used in construction in the UK; includes works, consultants. subcontracts, services

- AS: Australian Standards contracts - different contracts for a range of purchase types including constructions, consultancy, periodic supply of goods

- IET: Institution of Engineering and Technology which issue jointly agreed model forms covering the design, supply and installation of electrical, electronic and mechanical plant 'including special conditions for the ancillary development of software'

- CIPS: Chartered Institute of Procurement and Supply - CIPS has developed its own suites of standard forms of contract for IT functions including: supply and installation of computer equipment, support and maintenance of bespoke software, servicing of computer equipment.


LO3, AC 3.1

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

Which of the following should be applied when measuring frequency of on-time deliveries during a contract period?


Correct : B

Number of on-time deliveries can be quantified, then numerical measures can be applied.

Frequency of on-time deliveries is measured as on-time deliveries as a percentage of total no. of deliveries for period.

LO 2, AC 2.2


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

According to mailbox rule in some common law countries, at which point the offeree's acceptance will be effective?


Correct : D

When parties do not negotiate face-to-face, a key Question: becomes when

things like acceptances, rejections and revocations take effect. The general rule is that acceptances are effective on dispatch (when they are mailed). Everything else becomes effective when the offeror actually receives them. This idea is codified by the ''mailbox rule'' which states that acceptance is effective on dispatch, even before the offeror has received it. (The one minor exception to this rule involves option contracts for which acceptances are not effective until they are received by the offeror.)


- The Mailbox Rule

- CIPS study guide page 34

Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500