Your team needs a new board that:
only shows issues that are actively in progress
allows a separate area to prioritize incoming work
allows them to release issues from the Done column
Identify the correct solution to meet these requirements
Correct : E
A Kanban board with the backlog enabled meets all the requirements: it shows only in-progress issues (via column configuration), provides a separate area to prioritize incoming work (the Kanban backlog), and allows for releasing issues from the Done column (via version management or Kanban releases).
Start a Discussions
Vishnu is the Project Lead of the DEV project He can create new components inline while viewing DEV issues.
You should have the same ability as Vishnu. However, you can only select an existing component not create new ones inline.
Which change will definitely enable you to create new components inline?
Correct : A
To create new components inline, you must have the Administer Projects permission. This permission allows users to manage project configuration elements such as components, versions, and workflows. Granting this permission will enable you to perform the same actions as Vishnu.
Start a Discussions
Your team uses a company-managed Kanban project and needs a way to categorize issues as follows:
group issues by the project phase in which work will be started
assign a fixed start date and end date to each phase
move unresolved issues to the next phase
view reports of resolved issues by phase
Which product feature should be used to categorize the issues?
Correct : D
Start a Discussions
You want to see how unresolved issues are trending over a given period. Namely, on any given day, what is the average amount of time that issues were still unresolved.
What gadget displays this information?
Correct : B
The Average Age Chart shows the average age of unresolved issues over time. It helps visualize how long, on average, issues have been open on any given day, which directly reflects how unresolved issues are trending.
Start a Discussions
The UX team uses a custom issue type named Design in your team-managed project.
You want them to start entering the number of days spent and remaining on each of their issues.
What field must you add to the Design issue type?
Correct : B
The Time tracking field is required to allow users to enter the number of days (or time) spent and the remaining estimate on issues. Adding this field to the Design issue type enables tracking of effort in terms of logged and remaining time.