Question 1

Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.

How can the project manager configure this relationship?


Correct : C

In Workfront, cross-project predecessors allow dependencies between tasks across different projects. To ensure that Task 1 in Project 1 starts only after the final milestone of Project 2, the project manager must configure a cross-project predecessor linking the final milestone in Project 2 to Task 1 in Project 1. This establishes a dependency and aligns the timelines of the two projects.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer's time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.

Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?


Correct : B

The Workload Balancer in Workfront is used to compare planned hours against actual hours worked, providing a clear view of resource allocation and over-utilization. In this case, the project manager can use the Workload Balancer to demonstrate how the video designer's planned hours for the project differ from the actual hours spent. This helps the project manager make data-driven decisions about resource adjustments.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

Refer to the exhibit.

AD0-E903 Exam Question 3 Exhibit 1

What do the connector lines between tasks in a Gantt chart represent?


Correct : C

In Workfront, the connector lines in a Gantt chart represent the predecessor relationships between tasks. These lines show how one task depends on another, indicating the order in which tasks need to be completed. This helps project managers visualize task dependencies and how changes in one task can affect others in the timeline.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

A copywriter wants to see his incomplete tasks for projects to which he is assigned.

Which steps should the project manager take to create a custom Workfront report with this information?


Correct : C

To filter tasks that are incomplete and assigned to a specific user, the correct approach is to create a Task report, then filter by Task Status that is 'Not Equal' to Complete. Additionally, the Assignment filter should include the user's name to ensure only tasks assigned to the specified copywriter are shown.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

Which two statements are true about Groups and Teams? (Choose two.)


Correct : A, D

In Workfront, Teams are operational entities that can be assigned to tasks, while Groups are organizational entities that are not assignable to tasks. Additionally, work requests can be routed to both Groups and Teams, depending on how the organization is structured and how the routing is set up.