Curious about Actual AACE International PSP Certification (AACE-PSP) Exam Questions?
Here are sample AACE International Planning & Scheduling Professional (PSP) (AACE-PSP) Exam questions from real exam. You can get more AACE International PSP Certification (AACE-PSP) Exam premium practice questions at TestInsights.
If Activity E's duration changes to 4 months, what is the overall duration of the project.
Correct : B
Start a Discussions
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
Correct : C
Start a Discussions
If all other work proceeds according to the Baseline plan, how many times will the critical path change?
Correct : C
Start a Discussions
At the end of month one, did the delay to the parking structure foundation delay the project?
Correct : B
Start a Discussions
How could the structural steel drawing delay have been prevented?
Correct : A
Start a Discussions